ANOTHER PROJECT WAS SAFELY COMPLETED✓
AMS Group decommissioned at three separate energized substations in l week.
AMS safely pumped out all oil from 3 substations into two oil tanker trucks. PCB reports on file confirming non-hazardous oil and appropriate manifests.
Our team decommissioned the transformers on a staggered schedule, optimizing the equipment used at each location.
Consolidated all disassembled parts to ship full truck loads, maximizing space and revenue.
Safely closed out our project in a week without incident, meeting and exceeding client expectations.
AMS turnkeyed this project from start to finish and collaborated with site personnel to have it completed ahead of schedule and in accordance with both AMS and local site safety and environmental regulations.